PS29 Construction

Archive for May 2012

Mt. Sinai’s Pediatric Environmental Health Speciality Unit will come to PS 29 next Thursday, May 24 to speak with the parents and answer questions about health concerns associated with the ongoing construction work. The Pediatric Environmental Health Specialty Units (PEHSU) are a source of medical information and advice on environmental conditions that influence children’s health.  We [...]

MAY 10, 2012 UPDATE – RECAP OF SCA AND SCHOOL MTG.

Posted by: admin on: May 12, 2012

THE LETTER BELOW WAS SENT TO YVETTE KNIGHT (SCA PROJECT MANAGER) ON MAY 10, 2012 AS A RECAP OF THE SCA MEETING HELD WITH THE SCHOOL THAT SAME DAY. Yvette,  Thank you for the documents describing the terms.  It is quite an education.  We hope that going forward you will provide them to other parents before [...]

Construction Cleaning Procedure

Posted by: admin on: May 2, 2012

The following procedures are conducted everyday that construction work takes place. 3:30p.m. – 11:00 p.m. Exterior a/c units in the area of work and adjacent general area are covered with plastic with plywood placed over for added protection from unlikely falling debris staff is asked to close windows before leaving but there is a walkthrough [...]

Occupancy Letter for Rooms 303

Posted by: admin on: May 2, 2012

Good morning, Please be advised that the abatement work done on the exterior facades of room 303 and the third floor stairwell 2 window has been completed and the areas have been cleared for reoccupancy.  K029-41061.050212

At 12.49pm we received an email (below) from Yvette Knight at the SCA outlining some decisions they have made regarding communication between us moving forward, documents we requested, and responses to the questions we submitted last Thursday. SCA responses to the questions submitted on 4/25 and on 4/27. SCA response letter Proposed schedule PS 29K SCA [...]